Understanding 45Q: The Carbon Capture Tax Credit

Published :

Published :

Understanding 45Q: The Carbon Capture Tax Credit

Understanding 45Q: The Carbon Capture Tax Credit

Published :

Published :

With several states and a number of utilities adopting decarbonization goals, carbon capture and sequestration (CCS) and carbon capture, utilization and storage (CCUS) may find a role in an energy transition as coal and gas plants retrofitted with either technology could continue to operate.

What is the 45Q tax credit?

45Q is a performance-based tax credit incentivizing carbon capture and sequestration or utilization. Much like with the production tax credit (PTC) for wind, under 45Q, qualifying power generation and industrial facilities can “generate” a tax liability offset per captured tonne of carbon dioxide. The amount of the credit per tonne varies based on if the facility sequesters the carbon in permanent geological storage or captures the carbon for “utilization” in enhanced oil recovery (“EOR”) or other processes.

The original Section 45Q tax credit was enacted by the Energy Improvement and Extension Act of 2008 to incentivize the reduction of carbon dioxide (CO2) emissions from qualified facilities and support redeployment of CO2 energy through efforts such as enhanced oil recovery (EOR). Section 45Q tax credits were initially limited to 75 million tonnes. The Bipartisan Budget Act of 2018, enacted on February 9, 2018, substantially modified the Section 45Q tax credit to increase over time, expanded the credit to include other carbon oxides and eliminated the previous 75 million tonne cap. The enhanced 45Q credit linearly increases from $22.66 per tonne of carbon in 2017 to $50 per tonne in 2026 for carbon sequestration, and from $12.83 per tonne in 2017 to $35 per tonne in 2026 for EOR and other uses. The tax credits are provided for 12 years. An electric generating facility can utilize the credit if it removes at least 500,000 tonnes of carbon from the atmosphere during the taxable year. In June, the IRS proposed additional rules of commercial importance to project owners and potential investors, which is detailed in the latter half of this post.

Implication of rulemaking for power plant owners

Although several emission-intensive industries (chemical or fertilizer production, natural gas processing) have taken to the CCUS technology, the coal and gas-fired power plants in the power sector face a greater technical challenge capturing the carbon because of the lower concentrations of CO2 in the emissions stream. With the successful retrofit of CCS on the W.A. Parish Plant in Texas (referred to as Petra Nova) and increased development funding from the Department of Energy, interest in CCS retrofits have expanded.  The Petra Nova plant came online in 2017, notably on-time and within budget.  The Petra Nova CCS project captures approximately 90 percent (or roughly 1.4 million tonnes) of the CO2 from a 240 MW slipstream of flue gas. The captured CO2 is compressed and transported through an 80-mile pipeline to an operating oil field where it is utilized for EOR. Exhibit 1 provides a list of large-scale CCUS power generation projects currently under operation or advanced development within the United States.

Exhibit 1

The 45Q tax credits, like the wind protection tax credits, are valuable to tax-paying entities, referred to as tax equity.  The sale of tax equity is one major source of project funding.

Harnessing CCUS-friendly policies like 45Q could help flip the economics for the electric power sector back in favor of gas and coal generators. Exhibit 2 shows the capital costs of CCUS retrofits to existing coal power plants dropping to ~$1000/kW by 2030 as technology learning rates and economies of scale drive down the overall cost of capture. Deep decarbonization goals may require a diverse energy mix beyond just wind, solar and battery storage resources to ensure reliability, and CCUS could play a role as a dispatchable, backup alternative.

Notably, successful CCUS retrofit of existing power plants could potentially extend their lives. Since 2015 more than 70 GW of coal-fired generating capacity has retired in the U.S., and new coal plants continue to be added to the retirement roster due to sustained low natural gas prices, increased renewable generation, and high environmental compliance costs.

Although 45Q requires that eligible facilities begin construction by 2024 project owners are not deterred, as several commercial-scale CCUS projects are in the project pipeline. Companies like Enchant Energy for the San Juan coal plant and Minnkota for the Milton R. Young coal plant are hoping to build on the critical operational experience provided by the retrofit of Petra Nova and Boundary Dam coal-fired power plants. Decarbonization goals could result in retrofits for the growing fleet of combined-cycle gas plants as well, which is consistent with the CCGT plants included in the pipeline.

Given that these retrofit projects are highly capital-intensive and the pandemic has created some uncertainties in capital markets, there may be an extension beyond the January 1, 2024 deadline. EVA assumes that the time limit will be extended through 2030 to provide utilities or developers with more time to finalize investment decisions amidst the current market uncertainty.

Although reliable financial data sources are sparse, EVA’s analysis of 45Q suggests that Enhanced Oil Recovery (EOR) is currently more attractive to developers than geological storage despite the lower tax credit for EOR. This preference appears to be due to economic reasons and the difficulties associated with sequestration.  While the increased 45Q credits in the permanent storage scenario (b) partially offsets the lack of CO2-EOR sale revenue, the incremental cost of storage makes it a less attractive option than EOR.

Exhibit 2

(a) permanent sequestration (example: geological storage)
(b) enhanced oil recovery or other such utilization
EVA assumes the current construction deadline of 1/1/2024 to be extended through 2030.

Other Requirements and Key Elements

Following the “Carbon Guidance” released on Feb 19th 2020, shortly after (June 2nd 2020) the IRS published the long-awaited proposed regulations regarding the tax credit to provide additional clarity to eligible taxpayers. Some of the notable changes proposed in 2020 include:

  • Construction Start: Notice 2020-12 details two methods to establish that the construction has commenced before 1/1/2024 for a qualified facility or equipment: (1) The Physical Work Test requiring “physical work of a significant nature” on-site or off-site, and (2) 5% Safe Harbor requiring the taxpayer to incur at least 5% of the total cost of the carbon capture equipment to be installed at the qualified facility. Some examples of on-site/off-site physical work include excavations for installing foundations, installation of gathering lines to connect the facility to the carbon capture equipment, manufacture of mounting equipment such as racks or rails, and installation of components for carbon capture such as membranes, turbines, compressors and engines.
  • Continuity Safe Harbor: According to the continuity safe harbor mechanism, projects can claim the tax credit as long as carbon capture equipment is in service six years after the official construction start date. This reduces the uncertainty of whether the project qualifies for the credit as it provides leniency in demonstrating continuity over the entire period from project start to finish.
  • 80/20 Rule for Retrofit Projects: Existing carbon capture projects may qualify for the new, larger 45Q credits if equipment is added with a market value of at least 4 times the value of the existing equipment—a mechanism known as the “80-20 Rule”.
  • Credit Transfer Flexibility: By default, the Section 45Q credit is awarded to the taxpayer that owns the carbon capture equipment and physically or contractually ensures the storage or use of the captured carbon. The taxpayer, however, has the authority to transfer the credits to one or multiple entities that purchases the captured carbon to use or dispose of it, or to transfer the facility to a new owner or to a different site altogether.
  • Recapture Rules: To avoid the risk of recapture from being a barrier of financing projects, the proposed rule provides clarity on how and when tax credits are recaptured in the event of a carbon leak. The credits can be recaptured if the leaked carbon exceeds the amount of carbon disposed of or utilized in that taxable year. If the leaked amount is lesser than that captured, it does not trigger recapture. The taxpayer can simply claim the tax credit for the net amount disposed or utilized. The credit recapture period starts from the date the captured carbon is first injected or stored and ends five years after the taxpayer’s last credit. Leaks due to issues not in control of the taxpayer, such as volcanic activity or a terrorist attack are exempted from recapture.
  • Partnership Flip Structure: Partnership flip structures similar to wind tax equity investments are permitted to allocate the sequestration credits between project developers and equity investors.

The proposed rulemaking was largely welcomed by project developers; however, some amount of risk regarding the 45Q credits encouraging CCUS-related market activity remains. With the pandemic hitting pause on new investments, tax equity investors could be hard to come by, as uncertainty persists.. Additional regulatory changes, in the form of a timeline extension or direct cash payments instead of credits, may be needed to drive investments in this market.

Share
Top